Project Overview

As part of work on a major hydro electricity scheme, J N Bentley required the services of a specialist drilling and grouting contractor. The ground stabilisation work was to be undertaken in a remote area with difficult forest terrain and unmade roads.

Pennine worked continuously for a number of weeks taking advantage of the long summer days and ensuring that completion was ahead of schedule.


 

Result

Over 40 tonnes of OPC based grout was injected via an array over the length of the site. 

Technical Information

Drilling equipment:
Klemm 802